issue with the base line
Last Post 03 Jul 2009 06:00 AM by lakevy. 1 Replies.
AddThis - Bookmarking and Sharing ButtonPrinter Friendly
Sort:
PrevPrev NextNext
AuthorMessages
premUser is Offline
New Member
New Member
Send Private Message
Posts:1
prem

--
25 Jun 2009 08:27 AM QuoteQuoteReplyReply  
hi

I have updated the programme and there is no baseline selected, ie in the assign base line box, all the baselines are shown as "current project"

then my early start and finish date should match with BL start and BL finish, but for  activities which are progressed, the are  not matching why?

regards

prem

screen_shot.xls

lakevy
Posts:386
lakevy

--
03 Jul 2009 06:00 AM QuoteQuoteReplyReply  
after you create the baseline (in Maintain Baseline) you have to assign it using (Assign baseline). Try to use Project Start and Finish column instead of Expected Start/Fin