Dear Ahmet,,
I Hope u can help me, I had activity contain mason Carpenter, mason rebar, and mason concrete. All assigned in one activity say with duration 12 day, the budget unit of each mason distributed on all days (12day). After I did, I realized that I should distribute budget unit of mason concrete on 1st 6 days the mason rebar on 2sc 5 days the mason concrete at last day 1. so I know I should use Pocket planning and edit on recourse assignment isn’t it.?? Do u have method by global change to do this modification
Thanks
M.ganzouri
Dear all,
I found method alternative to Global change, by using Curve for distribute Mason. But curve not accurate with small duration . So any body has suggestion.