Wednesday, January 07, 2009

To be able to post message in forums, please login or register.

Registration is free (also spam-free)!

Alternate Layout for P6
Last Post 16 Nov 2008 06:21 AM by JPx2. 6 Replies.
Printer Friendly
Sort:
PrevPrev NextNext
AuthorMessages
seanmurrayUser is Offline
New Member
New Member
Posts:2
Avatar

--
07 Oct 2008 08:26 PM QuoteQuoteReplyReply  
Hi, this is my first post here, so I'd like to say hello to everybody.  I've been maintaining what I'd call a 'typical' (ie what I learned in classes, etc) P6 schedule on my job, and basically each week I update the % complete of each task and move the data date forward a week and i will get different end dates etc.

The client now wants a "baseline" schedule, but not in the typical sense (ie black line underneath each task).  He wants me to use my schedule as it is now and show percent completes for each task, but the tasks are not to move from week to week.  For example ...

if i have a task that goes from nov 1st to nov 5th, but it's only at 50% completion on nov 7th when I update, the updated schedule (dd=Nov 7) should still show the task going from the 1st to the 5th, and show it as being 50% complete.  Is this possible?

If this question is unclear, I can upload an image of what I'm looking for.  Thanks,

-Sean


Ahmet CetinUser is Offline
Master Member
Master Member
Posts:359
Avatar

--
08 Oct 2008 08:28 AM QuoteQuoteReplyReply  
Hello Sean,

Welcome to the community. To save and show the baseline, please follow the these steps:
1. Under Project menu select Maintain Baselines...
2. Click on Add button on the dialog box and select Save a copy of the current project as a new baseline
3. Under Project menu, select Assign Baselines...
4. In User Baselines Primary, select the baseline you've just created
5. Under View menu, select Bars...
6. In Bars dialog box, mark Primary Baseline and Baseline Milestone and click on OK.

If you follow these steps successfully, you should see the baseline bars below your Current Bars.

Hope this helps,

Ahmet Cetin


seanmurrayUser is Offline
New Member
New Member
Posts:2
Avatar

--
08 Oct 2008 12:35 PM QuoteQuoteReplyReply  
Thanks for the reply, Ahmet.  I have a bit of experience using P6, I've taken a basic course etc and I can set a baseline no problem, but what the client wants is (I think) something that I've seen before in Microsoft Project but not in P6.  Basically the task durations don't change, even if they are delayed ... It doesn't help much for forward planning, but I guess it's what they're used to.  I've attached an example of what I'm talking about, if you look at tasks 846 to 845, they show the tasks ending before the data date, but the tasks are not complete.  I'm not sure if Primavera has this capability or not, but I'd rather stay in P6 than convert to Project if at all possible.  Thanks

Attachment: 110835224871.pdf

tiltUser is Offline
Basic Member
Basic Member
Posts:48
Avatar

--
29 Oct 2008 07:48 PM QuoteQuoteReplyReply  
Sean, from your first post what I understand is that you will keep changing the % complete but the dates should not be recalculated. Did I understand you question correctly?
If yes, one thing I can think of is, update the % complete and actual hours etc as usual, but do not reschedule. You will stop rescheduling (no more F9). And also, do not change the data dates any more, let the data date be what it is.
Ahmet, would this work?
Cheers


seanmurray (guest)User is Offline
New Member
New Member
Posts:0
Avatar

--
29 Oct 2008 08:08 PM QuoteQuoteReplyReply  
Thanks for the reply. I ended up creating a new layout that shows the baseline only, and shows baseline start and baseline finish dates instead of actual start and finish dates. This way, I can still change data date, update the schedule and % completes, and change things to reflect the way they really are, and then I can just switch the layout view and print off a "static" version, complete with percentages. Certainly not perfect, but it's good enough. Thanks for taking the time to respond.


GerryUser is Offline
Advanced Member
Advanced Member
Posts:53
Avatar

--
04 Nov 2008 07:14 AM QuoteQuoteReplyReply  
Sean, your solution really helps. I also encounter some people that they prefer to see the schedule in its original state and they just want to see it with % complete bar. But, I guess this will be better if this is combined with progress line. I used to display progress line in my schedule when I was using P3 but this function seems to be missing in P6.


JPx2User is Offline
New Member
New Member
Posts:2
Avatar

--
16 Nov 2008 06:21 AM QuoteQuoteReplyReply  
Sean,
Could you email me this project schedule?
Thx
Jim Posey
jposey@bowenengineering.com




Quick Reply
toggle
 Username:
Subject:
Body:
Security Code:
Enter the code shown above:

Submit
Active Forums 4.1
Privacy Statement  |  Terms Of Use
Copyright 2007 by PrimaveraTools.com